Project Team
  • Client: Glenveagh Homes

  • Civil / Structural Engineer: DBFL

  • Quantity Surveyor: Glenveagh Homes

  • Works Contractor: Rossmore Civils

Client
  • Glenveagh Homes

Contractor

Rossmore Civils

Duration
December 2023 – June 2025
  • Site clearance over an area of 160,000m2 and enabling works including the construction of a fully serviced site compound and all temporary site access roads.
  • Installation of 7,000m of mainline foul and surface water drainage lines up to 750mm diameter,
  • Construction of all main line manholes, road gullies, separators and outfalls, with manholes up to a depth of 5.00m
  • Bulk excavation of 30,000m3 for a new Park with associated wetlands.
  • Disposal of circa 150,000m3 of excavated material off site. This involved the on-site processing of 70,000m3 of contaminated soil for reclassification to a different waste category.
  • Cropping of 900 nr. precast concrete piles and leave ready for incorporation into in-situ concrete pile caps.
  • Excavation for ground beams, foundations and pile caps to four apartment blocks. Filling and compaction of SR21 material to underside of FFL. Installation of all under-slab drainage and services.
  • Construction of 200m long piped diversion (600mm) of existing river to facilitate the construction of the Works.
  • Installation of 4,000m of PE watermain up to 250mm diameter, including all associated valves, fittings and house connections.
  • Installation of circa 45,000m of ducting pipework for power, comms, public lighting with all associated chambers, mini-pillars, micro pillars etc.
  • Hard landscaping to new park and wetlands, including the construction of a mixture of concrete and gravel footpaths (3,000m2), installation of landscape boulders, construction of 3 nr. in-situ concrete bridges and ground preparation for exercise area.