Civil / Structural Engineer: DAA
-
Construction Managers: DAA
-
Main Contractor: SLJV
Client
-
Dublin Airport Authority
Contractor
SLJV
Duration
May 2022 – May 2023
- Installation of 6.5m High Jet Blast Fencing to protect workers from Jet Blast during Aircraft manoeuvring.
- Demolition and Removal of existing life expired taxiway including subbase to a depth of up to 3.0m.
- Demolition and Removal of all existing Drainage, Electrical and Comms pipework.
- Excavation and Disposal from site of 35,000m3 of Unsuitable Material
- Construction of the Drainage and ducting infrastructure including 1,500m of Surface Water Pipework, 300m of In-situ Gatic Slot Drain, 500m of Precast Slot Drain, 76no. In-situ Concrete Manhole up to 2.1m and 5m deep, 60no. Precast Access/Outlet Boxes, Geo-cellular Stormwater Retention Tank. (112m long x 7m wide x 3m deep.
- 13,000m of 150mm Ducting
- 140no. Precast Chambers up to 1.5m2
- Construction of 10,000m2 of new Concrete Taxiway.
- Construction of 3,000m2 of Flexible Pavement Taxiway joining to Main Runway during 3 week – 24 hour shutdown period
- Reprofiling and Topsoiling entire works area