DUB56 – Data Centre Project, South Dublin
Client
- Confidential
Main Contractor
John Paul Construction
Duration
July 2016 – April 2017
- Completion of groundworks, drainage and utilities on Data Centre Project.
- Installation of site services including watermain, fire hydrant main and HDPE twin-wall storm drainage system and petrol interceptor.
- Installation of large banks of ducting & shutter and pour in-situ chambers.
- Excavate and install deep drainage (5.5m deep) and associated connections to live services on Belgard Road.
- Construction of road pavement to sub-base level and pour concrete footpaths & associated hard landscaping works.