Netcor PPK2 Civils Site Development
Client
- Jacobs
Main Contractor
John Paul Construction
Duration
January 2015 – November 2015
Works Completed include:
- Site Development of this 50 acre site.
- Disposal offsite of 80,000m3.
- Substructure excavations and structural fill, site works for a new data centre building,
- Site services construction including storm drainage 150mm-900mm dia.
- Foul drainage 100mm-225mm dia.
- Water and fire main 150 and 200mm,
- 900mm dia culverts,
- Installation of service ducting for data and electrical supply, site access roads and kerbing.
- Hard and soft landscaping including attenuation pond.