Project Name
AVDGS (Advanced Visual Docking Guidance System)
Client
  • Dublin Airport Authorities
Main Contractor

Balfour Beatty

Duration
September 2019 – May 2020

Works Completed include:

  • Civil Works associated with installation AVDGS Screens (Advanced Visual Docking Guidance System) screens at stands at pier 2, 3, 4 and apron 5G at Dublin Airport.
  • Breakout of Existing Pavement quality slabs to facilitate the installation of ducting, duct chambers and RC Bases for AVDGS screen poles.
  • Reduced level dig under removed slabs and full build up for reinstatement of PQ concrete slabs.
  • Hand Lay reinstatement of PQ Concrete slabs.
  • Construction of AVDGS Pole bases including holding down bolt sets.
  • Installation of RC cast in-situ Duct chambers and Precast duct chambers.
  • Installation of Protection Bollards around now AVDGS poles.
  • Ducting for emergency stop pedestals.