Project Name
Dublin Airport – Airside Pollution Control Works
Client
  • Dublin Airport Authorities
Main Contractor

Balfour Beatty

Duration
August 2011 – November 2011

Works Completed include:

  • Excavate, lay and backfill 1,457m of 1200mm dia precast concrete pipe.
  • Construct reinforced concrete cast insitu manholes: 13 nr
  • Install interceptors: 5 nr
  • Open cut crossing of existing runway and taxiway: 85m
  • Crossing of live runway by pipejacking method: 65m