Cork Airport – Airside Upgrade Works
Client
- Dublin Airport Authorities
Main Contractor
Balfour Beatty
Duration
November 2012 – December 2012
Works Completed include:
- Upgrade of 1,600 sq.m of aircraft taxi-way concrete pavement including:
- Dismount, set-aside and reinstate existing taxi-way lighting.
- Excavation & off-site disposal of existing pavement layers.
- Form new pavement comprising 150mm granular sub-base layer on geotextile with 375mm PQ concrete reinforced with A393 mesh including dowelled joints to existing pavement.
- Reinstatement of taxi-way delineation including thermoplastic linings.