Dublin Waste to Energy Civils Works Phase 2 Package Contract
Client
- Covanta Europe Engineering Ltd.
Construction Manager
PM Group
Duration
May 2016 – June 2017
Works Completed include:
- Construction of below ground structures including a 3,500m3 attenuation tank.
- Retention separators and associated temporary works including TW design for 150m of sheet-piled cofferdam walls up to 7.0m deep.
- The installation of all below ground services including 900m of fire hydrant ring main.
- 1,500m of storm water drainage.
- 2,200m of LV & ELV duct banks.
- 2,200m of buried earthing ring.
- Site fencing works include 165m of RC retaining wall.
- 495m of security perimeter fencing.
- 9,900m2 pavement construction works elements include:
- 4,000m3 capping layer construction.
- 1,485m3 subbase layer.
- 6,000t of flexible surfacing.