Project Name
Dublin Waste to Energy Civils Works Phase 2 Package Contract
Client
  • Covanta Europe Engineering Ltd.
Construction Manager

PM Group

Duration
May 2016 – June 2017

Works Completed include:

  • Construction of below ground structures including a 3,500m3 attenuation tank.
  • Retention separators and associated temporary works including TW design for 150m of sheet-piled cofferdam walls up to 7.0m deep.
  • The installation of all below ground services including 900m of fire hydrant ring main.
  • 1,500m of storm water drainage.
  • 2,200m of LV & ELV duct banks.
  • 2,200m of buried earthing ring.
  • Site fencing works include 165m of RC retaining wall.
  • 495m of security perimeter fencing.
  • 9,900m2 pavement construction works elements include:
  • 4,000m3 capping layer construction.
  • 1,485m3 subbase layer.
  • 6,000t of flexible surfacing.