Kinsealy Residential Development
Client
- O’Flynn Group
Main Contractor
Rossmore Civils Ltd
Duration
April 2018 – December 2018
Works Completed include:
- Site clearance and establish main compound
- Site Strip and house bases for show houses.
- Installation of all service and drainage along Kinsealy Lane alongside live traffic.
- Deep drainage (4m+ deep) included 370m of storm pipework and 370m of foul pipework.
- Installation of 2no. petrol interceptors.
- 30om of watermain and service ducts including traffic signal ducts.
- Implement a Traffic Management plan with its installation and removal on a daily basis.
- Realignment of Malahide Junction and installation of new ducting, pedestrian crossing, traffic signal lights and associated works.
- All surfacing works associated with this contract including asphalting to the realigned road and carparking spaces.
- Construction of cycle lane, pedestrian walkway and appropriate signage.