Project Name
Balgriffin Cemetry
Client
  • Fingal County Council
Main Contractor

Nevin Construction

Duration
July 2017 – December 2017

Works Completed include:

  • Site clearance an topsoil strip.
  • Disposal of 6000M3 of Material off-site.
  • Demolition of existing site structures and disposal of material offsite.
  • Installation of 1100m of site drainage and all associated works.
  • Excavation for and installation of attenuation tanks.
  • Installing 950m of services ducting and chambers.
  • Installation of 500m of new watermain.
  • Construction of 800 no. Headstone Plinths,
  • 1500m of paths and hearse-ways, new carpark and service yards.