Project Team
  • Construction Manager: FT2
  • Civil / Structural Engineer: Atkins
  • Main Contractor: Elliottt Group
  • Works Contractor: Rossmore Civils
Client
  • Echelon Data Centers
Contractor

Elliott Group

Duration
March 2023 – December 2025
  • Site clearance & demolition of existing structures

  • 40,000m3 of bulk & foundations excavation & disposal

  • WAC Testing and disposal of contaminated materials

  • 25,000m of specialist ducting

  • 3,000m of general ducting (PL, EV, CCTV, Fibre)

  • 1,000m of surface water drainage

  • 150m of stainless-steel oily water drainage

  • 1,400m of fire main, process main & water main

  • 10,000m2 of concrete hard standings, roads and footpaths 

  • Temporary works design and implementation

  • Construct temporary compounds, car parks & walkways

  • Partnering with stakeholders on design development, logistics planning and programme.