New Medical Devices Facility
Client
- Boston Scientific, Cork
Main Contractor
PJ Hegarty & Sons
Duration
February 2012 – December 2012
Project Description:
Site Clearance: 17,000m2, Bulk Excavation: 18,000m3, including 12,500m3 of limestone rock
Process excavated rock onsite: 7,900m3 disposal offsite: 9,500m3
Imported Fill to: 5,300m3, New Roads and carparks: 15,100m2
Installation of Storm Water pipe work and attenuation system.
Installation of Foul lines and live connections.
Installation of 2nr petrol interceptors
Installation of Class C MDPE Watermain: 372m