Project Name
Site Development Works Contract
Client
  • GE Healthcare
Construction Manager

M+W Group

Duration
November 2017 – February 2018

Works Completed include:

  • Establish site compound for project including provision of temporary services.
  • Initial enabling works included for site clearance and 38kv service diversion of overhead powerline.
  • Bulk excavation of 43,000m3 was treated with lime and placed within the fill area as stabilized material.
  • Excavation of Attenuation pond 10,000m3 to control surface water discharge on site.
  • Installation of works to storm outfall including construction of large insitu headwall, automated penstock, associated pipework with connection to storm water pipework.