Holiday Inn
Client
- Cara Shore Hotels
Main Contractor
Stewarts
Duration
November 2018 – June 2020
Works Completed include:
- Site Clearance 12,000m2.
- Topsoil Strip and disposal of site 12,000m2.
- Bulk excavation and Disposal offsite 15,000m3.
- Installation of Piling mat and excavation of Pile caps.
- Installation of Storm and Foul Drainage 1,500m.
- Installation of 150mm water main and connection to existing. 300m.
- Under slab drainage and Services.
- 1,000m3 Attenuation tank, incl. installation of temp sheet piles to allow tank to be installed on site boundary.
- Bulk excavation of underground water tank and backfilling 1,500m3.
- Deep drainage road crossing, across public road to facilitate connection to existing services.
- Ducting for signage and street lighting.
- ESB Ducting and connection to existing substation.