Project Name
Grifols Phase 2
Client
  • Grifols
Main Contractor

Stewarts

Duration
November 2016 – August 2018

Works Completed include:

  • Site Clearance and Topsoil Strip 21,000m2
  • Excavation and blinding of pads
  • Bulk filling of building footprint, car parks and logistics yard.
  • Bulk Excavation and off site of Existing stock piles on site 41,000m3
  • Excavation and Formation of Attenuation pond 2,000m3
  • Installation of Foul and Storm Drainage
  • Installation of all water main and connection to existing
  • Installation of MV LV and communications ducting
  • Bulk excavation of and construction of radius underground RC tank and backfill
  • All Paving, Kerbing and Finishes 2,500m2