Civil / Structural Engineer: Mountpark
-
Construction Managers: ISG Group
-
Works Contractor: Rossmore Civils
Client
-
MLEU Dubin Limited
Contractor
Rossmore Civils
Duration
July 2022 – May 2023
- Bulk Excavation and Disposal off site of 32,000m3 of soil. Excavation and installation of 1,450m3 capacity ‘Ecocell’ modular geo-void attenuation tank system with associated protective membranes and pipe work.
- Excavation and construction of concrete pad foundations for structural steel columns. Preparation of sub-floor for circa 15,200m2 insitu concrete floor slab.
- Installation of approx. 1,350m of foul and storm water drainage throughout the site including pumping stations and all associated manholes and gullies. Installation of 1230m welded 150mm PE watermain pipe, including all associated valves, fittings and chambers.
- Installation of 17,000m of ducting including, LV, MV ducting, site lighting, CCTV, telecoms, car charging and associated access chambers. Construction of two ESB MV Substation including coordination with ESB Networks.
- Construction of 7100m2 of non permeable and permeable paving asphalt surfacing to roads and car park areas. Construction of 300mm thick reinforced in-situ concrete slab for sprinkler tank.
- Undertaking of all landscaping works such as topsoiling, grass seeding, bark mulch, wildflower meadow, trees, shrub planting and associated annual maintenance works.