Project Name
Dublin Waste to Energy Civils Works Phase 1 Package Contract
Client
  • Covanta Europe Engineering Ltd.
Construction Manager

PM Group

Duration
September 2015 – April 2016

Works Completed include:

  • Construction of new permanent entrance and public road realignment under full-time traffic management plan in consultation with local authority and public utilities bodies.
  • Installation of site hoardings, excavations, services installation.
  • De-sludging and void-filling of an existing brick arch culvert.
  • Full road and footpaths construction to new horizontal and vertical alignment.