Polmadie Glasgow

Glasgow Lime Stabilisation

Glasgow Lime Stabilisation

Glasgow Lime Stabilisation

Glasgow Lime Stabilisation

Client: Bear Scotland

Main Contractor: John Paul Construction

Duration : May 2012 to January 2013

Project Description:
Full earthworks on this brownfield heavily contaminated site of 23,000 sq.m.
Earthworks cut/fill in heavily contaminated soils and soft ground improvement techniques were utilised in minimising off-site disposal and import of fill.
Rossmore also installed the surface water (including SUDS attenuation pond) and foul drainage systems and utility ducting.
A 450mm diameter outfall pipeline was constructed across the live M74 motorway, junction 1.