Lisheen Windfarm

Lisheen Access Road

Lisheen Turbine Base

Lisheen Windfarm Culvert

Lisheen Windfarm Road

Lisheen Windfarm Borrow Pit

Client: Bord Gais Eireann
Main Contractor: Balfour Beatty Ireland
Duration : July 2012 – May 2013

Extension to existing live windfarm.
Scope of work includes:

  • Excavation of 20,000 m3 for bases to 12 no. wind turbine generators
  • Construction of 12 no. crane hardstandings (13,100 m2)
  • Construction of 7 Km of access tracks (35,300 m2) of which 2.20 km / 10,900 m2 is a floating road construction
  • Excavate rock from on site borrow pit, crush to 6F1 spec for reuse in the works (6,500 m3)
  • Installation of 3 no. box culverts (3m x 3m) approx 30 linear metres
  • Duct trenching and backfilling (6 Km) incl. installation of approx 30,000 m ducts
  • Backfilling and reinstatement, and disposal of surplus material