ESB Aghada Generating Station Cork

Client: P J Hegarty

Duration: January 2010 – March 2010

Scope:

Laying of new stormwater pipe line, 225/450mm

  • Piperun: 70m, Avg. Depth: 2.5m. Pipe laid in existing carriageway. 5 no. 1350 dia. P.C. Concrete manholes.
  • Installation of 2 no. interceptors, one on new line and one on existing.

Excavation of existing carpark and construction and placing of sub-base for proposed new carriageway.

Placing new stormwater pipes for proposed carriageway.

Lay ducting to proposed new security station.

Excavate foundations for proposed security station.

Lay kerb to proposed carriageway.

Complete new landscaping works.