Eye Landfill

Eye Landfill Peterborough

Rossmore Civils at Eye

Rossmore Civils working at Eye Landfill

Cell 2 Construction:

Excavate unsuitable material in cell = 9,500m3

Cut / Fill material to construct cell = 24,106m3

Install back of wall drainage 141m

Install clay liner to cell including cell batters/bunds = 23,000m3

Place geotextile and install drainage layer of stone over engineered clay 5,400m3

 

Clay Cap:

Prepare ground and trim regulating layer = 80,000m

Place one meter of engineered clay to cap off landfill = 80,000m3

Place 200mm of protection layer to cover engineered clay = 16,000m3